The short answer
There is no reliable universal lead time for a custom product. Build a project schedule from approved specifications, sample and tooling milestones, material availability, factory capacity, inspection and the delivery route, with named responsibilities for each decision.
Build a milestone schedule
List briefing, artwork or engineering, sample preparation, sample transit, review, revisions, tooling, material procurement, production, inspection, packing and delivery. Some activities may overlap; others cannot start before an approval. Ask the project team to identify the actual dependencies instead of adding generic factory-day estimates together.
Separate three different clocks
Development time covers the work needed to reach an approved design. Production time covers the agreed batch after its release conditions are met. Transport time begins at the specified handover or booking stage and must state whether customs and final delivery are included. [1]
An estimate described simply as shipping in two weeks does not tell you which clock is being measured. Confirm the starting event, finishing event and calendar assumptions for every quoted duration.
Use approval gates to control revisions
Agree who can approve artwork, sample changes and tooling. Record the approved version and return consolidated comments. A change to dimensions after tooling has started can affect both cost and schedule; a supplier should assess the effect before the change is accepted.
Ask whether the sample proves appearance, fit or function. An appearance model does not necessarily complete engineering validation, and a stock sample does not necessarily authorise your customised production run.
Plan backward from the required arrival
- State the destination and the date goods must be ready for use or sale. - Identify review and transport contingencies with the responsible parties. - Confirm inspection and payment-release requirements before booking. - Reconfirm capacity and material availability when the order is approved.
For an event or seasonal launch, request a decision date after which scope or delivery choices must change. Avoid promising customers a fixed arrival date based only on a preliminary supplier estimate.
Questions buyers ask
Is a factory lead-time estimate a door-to-door delivery promise?
No. Clarify the starting and ending events, then add the separate sample, inspection, booking, customs and final-delivery stages relevant to the project.
What should happen when artwork changes after approval?
Identify the revision and obtain an assessment of its cost and schedule effect before authorising the change. Some changes can affect tooling or previously approved samples.
Sources and references
Official guidance and primary references relevant to this article. Check the current product scope and destination requirements before making a purchasing decision.
Plan your next step
Share the product, quantities, intended use and destination. WOW can help scope sourcing, samples and the production enquiry.
Explore the relevant service Start your project